#40 RESOLVED facilities
Marconi Court Level 3 comms-room air-conditioning failed; temperature climbing
| Reported by: | People & Places | Owned by: | G. Naismith (Facilities) |
|---|---|---|---|
| Priority: | P2 | Milestone: | |
| Component: | Facilities / HVAC (Chelmsford) | Version: | |
| Keywords: | Cc: | ||
| Desk: | Facilities | Legacy ref: | DEVCON-1547 |
Description
The dedicated A/C unit for the Level 3 comms room (which houses the CMS servers) failed; room temperature climbed past the rated ceiling on portables alone. If the CMS servers throttle or shut down, the whole estate's dwell schedule drifts.
Attachments (0)
Change History (3)
comment:1 by , 13 years ago
comment:2 by , 13 years ago
Agreed — if that room hits shutdown, every corridor loses its schedule at once. Escalate the contractor hard.
comment:3 by , 13 years ago
Emergency call-out, new compressor fitted, room back to 19°C. Added a temperature alarm on the comms room to the monitoring so we get warning next time. Closing.
Note:
See TracTickets
for help on using tickets.
Compressor gone. Two portables not keeping up, room at 31°C. This can't wait for next week.